Risky Business

For most people Risky Business invokes an image of Tom Cruise dancing to Old Time Rock and Roll in a pink shirt and sports socks. But to me it seemed an apt title for a recent report I wrote for Tunnels & Tunnelling International on insuring major tunnelling projects.

Risk 2

Back in the late 1990s, the tunnelling industry was reeling from high profile incidents on tunnels all over the world from fire and flooding on Denmark’s Storebaelt Crossing to the 1994 Heathrow Tunnel Collapse. In response to fears that tunnel projects were becoming uninsurable, the Association of British Insurers, and the British Tunnelling Society joined forces to create a new benchmark for best practice. Published in 2003 the “Joint Code of Practice for Risk Management of Tunnel Works in the UK” was followed by an international version in 2006 named the “Code of Practice for Risk Management of Tunnel Works”. These codes became known worldwide as the Tunnel Code of Practice, or TCOP and over a decade later it is now under review.

Insurers say that development of the code was an important step in building confidence in tunnelling projects. “It has led to tunnelling projects being more insurable today,” explains Cedric Wong, senior engineering underwriter and vice president of projects and global markets at Swiss Re Corporate Solutions. “It doesn’t guarantee success but it gives the best possible chance of a successful outcome if it is followed and implemented. When we are presented with a tunnelling project by a broker, we look at the information provided by the client, contractor and we benchmark it against the TCOP,” he says. “We can assess if they have taken a risk based approach in choosing the original tunnel alignment, have they procured based on both quality and cost, have established a risk management framework, are they using risk registers, have they got design checkers? We assess the project and if it aligns with the code and if we determine that risk management is solid there is a good chance of insurability.”

 

“The positive work done on projects like Crossrail gives insurers a good deal of confidence that technically complex tunnelling risk can still be undertaken,”

Cedric Wong, senior engineering underwriter, Swiss Re Corporate Solutions

Complexity is inevitable when building a new GBP 15bn (USD 20bn) railway with 42km of new railway tunnel using eight TBMs, along with construction of a further 18km of station tunnels and interchanges as well as 9 new stations beneath the UK’s capital city – making it inherently risky. “The mitigating factors to that were that London had relatively successful projects before with the Jubilee Line extension and the Channel Tunnel Rail Link. The geological model of London is really well known. The presentation of the Crossrail project in terms of benchmarking against the TCOP showed a really high level of compliance which gave us confidence that there was a high chance of success on the project,” says Wong whose firm Swiss Re Corporate Solutions took the lead position on the insurance programme. “The other factors that convinced us was the level of retention that the client was willing to take, set deductibles reasonably high. The higher the deductible is the lower the insurance premium and what that demonstrates to us is a real confidence in their own risk management.” At the same time, Crossrail were interested in the insurers’ risk management activities, which Wong describes as a complementary risk management regime. “They were keen for us to share our experience of engineering and construction claims and the associated lessons learnt from projects around the world. Throughout the changing risk profile of Crossrail, we select the industry risk experts that we think are most suitable for the job. These are experts, people who can add value.”

This risk engineering programme is a critical part of such projects for the insurance industry. On Crossrail for example there are 28 different insurers backing the scheme who are reassured thorough the risk management approach of the leading insurer. But before any of these firms could be appointed, Crossrail needed to work with a broker to determine the appropriate insurance structure and levels of cover required for this mega- project. And its sheer scale meant that it had to be tackled differently from the outset with the contract being tendered through the Official Journal of the European Union (OJEU).

“Brokers had to go through a tender to demonstrate that they had the technical knowledge, ability and experience to advise Crossrail on the appropriate insurances for the project,” explains Sarah Bickerstaff, executive partner in construction services at the tender winning insurance broker Arthur J Gallagher. “We learned about what they were going to build and really became part of the delivery team. We worked with Crossrail to understand what their appetite for risk was, what their approach was going to be and to explain to them their options and the pros and cons,” she says.

The earliest fundamental aspect of this was whether Crossrail would procure Contractors’ All Risk (CAR) and Third Party Liability (TPL) insurance through an owner controlled, or a contractor controlled route where the contractor places the insurances for their element of the contract. For a scheme the size of Crossrail, a contractor controlled policy would have meant a large number of different policies with a range of excesses and cover. “It wouldn’t give Crossrail control of the cover and the quality of insurer and the budgetary stability in terms of premium. The whole aim was to keep the project on target, on budget and so therefore Crossrail took control of the insurances,” says Bickerstaff.

Contractors’ All Risks (CAR) insurance is the cover for material damage that could occur on a project. The project also required third partly liability (TPL) insurance covering any damage to third parties such as buildings, infrastructure or people affected by an incident. For Crossrail it was crucial to have high quality cover, over the lifetime of construction which was nine years, and with fixed premiums to give long term budget certainty. This was a challenge for the insurance industry which typically introduces break clauses in project insurance policies which allow insurers to re-evaluate their position throughout the construction period.

“One of the key drivers was certainty of cover for the entire nine-year construction period. This had never been achieved in the insurance market before,”

Sarah Bickerstaff, executive partner in construction services, Arthur J Gallagher

“They needed to have absolute confidence that the insurers would support the programme to the end of the project irrespective of claims experience.” It’s typical that a panel of insurers would be required to cover a project of this size. With such high values of risk running into billions other insurers would need to participate in the project. “It is like layers of a cake really. You buy elements of cover in acceptable tiers up to a level where Crossrail thought they had bought adequate protection given the likelihood of loss and given the potential severity of that loss,” says Bickerstaff.

To ensure that the level was appropriate AJ Gallagher provided Crossrail with benchmark figures from other major projects before taking the scheme to market. By early 2009 Crossrail were ready to begin procurement, which by moving through the OJEU process, was being undertaken in a new way. “The challenge for us as brokers was that this was the first major project insurance policy to be procured through the OJEU rules. It had to be done through a data room so all firms had the same access to information. This is a people driven industry so to get them all to go to an electronic data room and pull the information out was something that we had to educate the market on,” says Bickerstaff.

Eight years later and with the tunnelling complete, the Crossrail project has been truly ground breaking from a risk management and insurance point of view. But it isn’t over yet – the insurance coverage continues until the rail is operational – and the risk profile has evolved from a tunnel collapse type failures to fire risk within the completed stations – which is the maximum exposure scenario for insurers.

  • The full article can be viewed here